Hearing Focuses on Mistakes Made on Bay Bridge

By: AP Email
By: AP Email
MGN Online

MGN Online

SAN FRANCISCO (AP) - Government and private engineers told a state Senate commission that pressure to complete the new $6.4 billion eastern span of the San Francisco-Oakland Bay Bridge led to cracked welds and other subpar work on the crossing.

The testimony Friday before the state Senate's Transportation and Housing Committee did not conclude the new span is unsafe, but highlighted construction mistakes that could have been prevented, and which may lead to costly future repairs.

Metallurgy experts including James Merrill, an engineer who oversaw inspections of key bridge pieces, testified that defective seismic safety rods that failed last March were made of a corrosion-prone steel that should never have been used.

Merrill said despite warnings that the rods were subpar the California Department of Transportation approved them.


Comments are posted from viewers like you and do not always reflect the views of this station.
powered by Disqus
KOLO-TV 4850 Ampere Drive Reno, NV 89502
Gray Television, Inc. - Copyright © 2002-2014 - Designed by Gray Digital Media - Powered by Clickability 241878331